PMI updated the PMP exam on 9 July 2026. If you sit the exam now, you take the new version, which is based on a new Examination Content Outline. Here is what changed and what it means for your preparation.
The new domain weights
| Domain | Share of the exam |
|---|---|
| People | 33% |
| Process | 41% |
| Business Environment | 26% |
The biggest shift is Business Environment, which grows from a small part of the old exam to about a quarter of the new one. It covers governance, compliance (including regulatory, safety and sustainability requirements), benefits and value, change control, risk, and how outside changes affect a project.
Format: 180 questions in 240 minutes
The exam has 180 questions, of which 170 are scored and 10 are unscored pretest questions that you cannot tell apart. You have 240 minutes. Questions are more scenario-based: you are given a situation and asked what the project manager should do, often in predictive, agile or hybrid settings.
What to change in your study plan
- Spend more time on governance, compliance, benefits realisation and risk, not only on scheduling and cost formulas.
- Practise judgement questions: for most scenarios, the best answer is to understand the situation, involve the right people and follow the agreed process before escalating.
- Keep earned value basics (CPI, SPI, CV, SV) fresh; they still appear, but as part of scenarios.
- Know when an adaptive or hybrid approach fits better than a predictive one.
- Take timed practice: 240 minutes is a long exam, and pacing matters.
What did not change
PMP is still pass or fail, and PMI does not publish a fixed pass mark. Eligibility rules and fees are set by PMI and can change, so always confirm them on the official PMI website before you book.