PMI · PMP

Project Management Professional practice questions

Experienced project managers working with predictive, agile and hybrid approaches

Pass markNot published (pass or fail)
Questions in the exam180
Time allowed240 min
Practice questions here50

What the PMP exam covers

Exam content outline from July 2026
People33%
Process41%
Business environment26%

Sample PMP questions

Five of the 50 practice questions, each with its answer and explanation.

People

Two senior team members disagree strongly about a technical approach, and the conflict is slowing the work. What should the project manager do first?

  1. Remove one member from the team
  2. Meet both to understand their positions and work toward a collaborative solution
  3. Escalate to the sponsor
  4. Choose the approach the project manager prefers
Show the answer

B. Meet both to understand their positions and work toward a collaborative solution

Collaborating to resolve the underlying issue usually gives the most lasting result. Escalation comes after the team has tried to resolve it.

People

A new team is forming and members are polite but unsure of their roles. Which action helps most?

  1. Wait for the team to sort it out
  2. Facilitate the creation of a team charter with ground rules and roles
  3. Assign tasks without discussion
  4. Schedule a performance review
Show the answer

B. Facilitate the creation of a team charter with ground rules and roles

A team charter sets shared expectations early, which helps a team move through the forming stage.

People

A key stakeholder has stopped attending reviews and seems unhappy. What should the project manager do?

  1. Meet the stakeholder to understand their concerns and update the engagement approach
  2. Send them the meeting minutes only
  3. Report them to their manager
  4. Remove them from the distribution list
Show the answer

A. Meet the stakeholder to understand their concerns and update the engagement approach

Low engagement is a signal to re-assess and adjust how the stakeholder is engaged.

People

A team member lacks a skill needed for an upcoming task. What is the best first response?

  1. Replace the team member
  2. Ignore it and hope the task goes well
  3. Arrange coaching or training, or pair them with an experienced colleague
  4. Do the task yourself
Show the answer

C. Arrange coaching or training, or pair them with an experienced colleague

Developing team capability is a core leadership responsibility and supports long-term performance.

People

Which leadership style suits a self-organising agile team best?

  1. Laissez-faire with no support
  2. Transactional only
  3. Servant leadership
  4. Autocratic
Show the answer

C. Servant leadership

Servant leaders remove impediments and support the team rather than directing every task.